Jal Jeevan Mission-District Dashboard

Heirarchy / District Progress
Total Block :
Total Panchayat :
Total Villages :
Population :
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Certified :
HO Villages :
Scheme Details
JJM Scheme :
JJM Village :
Jal Nigam Scheme :
Jal Nigam Village :
JJM + Jal Nigam Scheme :
JJM + Jal Nigam Village :
Village Status
Urbanized Villages :
Un Inhabitant :
less than 100 Population :
NGO :
NTD :
Agency Progress Details
Sr.No. Agency No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 GA INFRA - BABA (JV) 137 244 53784 49338 91.73% 148 51
2 WELSPUN 262 748 183056 175465 95.85% 515 41
Total 399 992 236840 224803 94.92% 663 92
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Details(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Components Wise Physical Progress
Sr.No. Components Target Achivement %
1 2 3 4 5
1 Tubewell 399 392 98.25
2 Pump House 399 354 88.72
3 Chlorination system 182 138 75.82
4 OHT 399 371/152 92.98
5 Distribution (Line Laying in Km.) 5439 5332 98.03
6 Solar Plant 385 284 73.77
7 F.H.T.C. 251779 239151 94.98
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 1406 1382 98.29
10 Villages where 100 % road restoration completed 97065 58819 60.60
11 Comissioning of Village 992 551 55.54
12 Regular water supply 992 547 55.14
;